"Sovelmash" D&E construction site today Asphalt paving, installation of heating mains and other activities

2
13KB

​​📌"Sovelmash" D&E construction site today | Asphalt paving, installation of heating mains and other activities 

 

At the main entrance to the O&A, the ground level has grown considerably from what you may have seen in one of the latest videos. The geotextile was installed and backfilling with sand commenced. This area will be levelled and prepared for asphalt paving, and so will be the area at the rear of the building, near the ramp. 

 

Due to the fact that the level of the heating mains utilities turned out to be higher than expected, it was necessary to dismantle the concrete bedding and dig a bit deeper in order to bypass the utilities. As of today, these tasks have been completed. 

 

Watch the video https://youtu.be/GwBaA-k3exw

for an overview of the work performed at the construction site.

Participate in the project by registering through our link

https://reg.solargroup.pro/amx480/06

https://reg.solargroup.pro/amx480

 

Like
Love
Yay
6
Pesquisar
Categorias
Leia mais
Outro
시원한 풍경
Por Ljino K1004 2023-07-15 01:52:53 6 7KB
Dance
Pi Network的愿景
Pi Network的愿景    ...
Por Fjj Lwzh 2023-04-03 01:29:36 1 14KB
Outro
여행
산사의 풍경3
Por Hyuntae Park 2023-08-04 09:19:18 5 6KB
Início
Pi network
Tương lai tươi sáng của các pi thủ.
Por Anhkiet77 Huynh 2023-06-10 13:34:32 12 11KB
Networking
Solargroup in China
​​📌SOLARGROUP in China | Day 1 | At the world's largest factory producing electric motors and...
Por Konan Firmin Kouakou 2023-07-27 19:44:51 3 9KB