Progress of BETI

2
9KB

​​📌Earthwork, finishing and other activities | "Sovelmash" D&E construction 

 

Diverse and extensive work is now being carried out at the construction site. 

 

✅ The area behind the building has been levelled and prepared for asphalt paving. 

 

✅ On the left-hand side of the entrance to the building: 

 

— work is underway to install the grounding. A temporary road has been built, and all water supply utilities, storm water drainage and so on have been completed; 

 

— the work of extending the Internet and all low-current networks is still to be carried out; 

 

— the input is being grounded in the area where the deep electrical input to the building is made, these are the four doors behind which the transformers are located. In order to route the wires inside the building, work is being done to prepare the input itself. Once these tasks are completed, the building will have a stable voltage supply; 

 

— all manholes are at level 0 and it will soon be possible to start removing the temporary road slabs to perform final levelling of the site and to make preparations for the future asphalt paving; 

 

  the temporary fence has been dismantled and its removal will continue. 

 

✅ In front of the entrance to the building: 

 

— the site has been levelled and the plate compactor is in operation; 

 

— a truck with heating radiators has been unloaded. 

 

✅ On the right-hand side of the entrance to the building: 

 

— the earthwork is underway: trays have been installed - they have been waterproofed, filled with sand, and you can already observe the pipes being welded together. You can see the sewer manholes, the expansion joints installed, the fully assembled waterproofed chamber through which heat will be supplied. 

 

✅ In the O&A: 

 

— on the 1st floor of the O&A, work continues on the installation of interior glass partitions and frames as well as finishing work in the staircase shafts, both inside and outside; 

 

— heating work has started on the 2nd floor of the office and amenity building; tiling has been done on the 2nd floor mezzanine and the electrical networks are nearing completion (the degree of readiness for the electrical networks is quite high); 

 

— on the third floor of the O&A, the heating distribution and electrification have already been completed. 

 

The final stage of installing the elevators is underway. 

 

Watch the video https://youtu.be/xFybMd6afEE

for more details. 

 

The work currently underway is quite extensive and requires everyone's attention for successful implementation of the project!

https://reg.solargroup.pro/amx480/06

https://reg.solargroup.pro/amx480

 

Like
Yay
6
Suche
Kategorien
Mehr lesen
Andere
비온 뒤 경치
Von Hyuntae Park 2023-07-24 06:55:30 6 6KB
Andere
美丽中国乡村
绿水青山就是金山银山!
Von Yh Lin 2023-09-12 02:14:28 0 8KB
Andere
台灣之美麗風景
美麗的~台南蝙蝠洞瀑布😍😃
Von Lin5 88589 2023-06-26 21:38:21 3 8KB
Art
沉得住气,踏实走好当下每一步
在抵达目标之前,我们都要走一段蜿蜒漫长的路。走到半途是最困难的,因为已经付出了很多,却还没看到尽头。此时,只要沉得住气,踏实走好当下每一步,生活自会给你满意的结果。新的一天,早安!
Von Liu Jingdong 2023-07-27 22:53:58 3 7KB
Andere
Pi the digital asset of the futurePi the digital asset of the future
Exhaustion of resources, war, natural disasters, epidemics. The greenhouse effect became the...
Von Giang dni 2023-06-26 23:50:06 3 10KB