Résultats of the week in the projet "Duyunov's motors"
📌Results of the week in the project "Duyunov's motors"
Summary of the work that was carried out at the "Sovelmash" construction site over the last week.
✅The geotextile was installed at the main entrance to the O&A building and backfilling with sand commenced. This area is being prepared for asphalt paving, and so is the area at the rear of the building, near the ramp.
✅Earthwork started outside the site to close the heating line. Bypassing of the utilities that had been located above the planned level was carried out. The heating mains pipes were laid, welded, the leakage control system was connected and other activities were in progress.
✅Inside the building, the employees of "Sovelmash" continued the installation of the heating equipment for the heat distribution station.
✅The temporary fence units were dismantled and are now gradually being removed. A part of the temporary road was dismantled for further laying of utilities.
✅A platform has been assembled for the installation of ventilation and air conditioning equipment, which will reduce the vibration load of the entire building.
✅The trench for the installation of outdoor lighting utilities was made.
✅Inside the building, the work was underway to install lighting.
✅The control and land survey of the installed external water supply lines was carried out in order to map the data onto the engineering and topographic plan of Moscow.
By the end of the 3rd quarter of 2023, "Sovelmash" is to connect all the utilities, carry out landscaping and other construction work. In order to complete these tasks in time, the funding needs to be accelerated. Now the support of every investor is important for the company!