Asphalt paving and interior finishing of the 'Sovelmash" D&E

0
10K

Engineering centre construction 

 

In the past week, the construction of the design and engineering technology department progressed on different fronts. 

 

Finishing layers of asphalt were paved, and a permanent fence was installed on the side of the building where the engineering networks were completed. 

 

A wide range of work was carried out inside the D&E. 

 

• In the office and amenity building, equipment was installed to provide access control with magnetic cards. 

• Heat was supplied to the water supply systems in order to switch to the permanent heating circuit. 

• The members of the commission for acceptance of heating networks were appointed under the chairmanship of Dmitriy Duyunov. The commission will start work next week. 

• For the time being, heat guns are operating in the O&A to maintain the temperature required for finishing work. 

• Floor screeding was completed on the second and third floors of the O&A. 

• The O&A walls are being prepared for painting. The stairwell has already been painted. 

• The ventilation system is almost fully mounted in the O&A building. 

• Installation of the lighting fixtures is in progress. 

• The cables were routed to connect power supply. 

• Fire protection systems were being installed. 

• The new laser unit has been assembled and its commissioning is now underway. 

• Plumbing fixtures for the first floor of the O&A building and locker room lockers were delivered. 

 

Document management 

 

Along with that, the specialists were working hard to prepare the documents for the application to obtain the statement on the completion of construction. 

 

Preparations for production of angle grinders 

 

Equipment and materials were packed for shipping from China to "Sovelmash". One container is fully packed with components for the angle grinder. 

 

We remind you that the first round of the SOLARGROUP lottery is underway aiming to accelerate the project funding. By investing in October, you get cashback and the opportunity to increase your share in the project by 2.5 times, as well as win an electric car and electric motorcycle.

Like
Yay
Wow
Love
Haha
Angry
15
Buscar
Categorías
Read More
Home
Pi network
Cuối tuần vui vẻ nha các pi thủ.
By Anhkiet77 Huynh 2023-06-10 12:48:58 10 11K
Home
风格
一种传承就是一种文化!
By Yh Lin 2023-04-18 16:09:55 4 8K
Other
Asphalt paving and interior finishing of the 'Sovelmash" D&E
Engineering centre construction    In the past week, the construction of the design and...
By Konan Firmin Kouakou 2023-10-25 20:12:28 0 10K
Wellness
오늘도 Pi로 활기차게 시작하세요
비가오는 흐린날씨지만 pi가 있어 즐거울수 있네요 오늘도 pi와 활기찬 하루 되세요~~
By J221 40584 2023-12-12 00:02:52 1 8K
Other
여행
#바다# 
By Hyuntae Park 2023-07-21 04:12:52 5 6K