Key project news for the week
In the outgoing week, the outdoor construction work was hampered by the rain. However, at the end of the week, the construction workers made use of the dry weather: they started paving asphalt on the right side of the D&E building and installing the pipeline in place of the storm sewer drilling.
In addition to this, the following tasks were tackled at the construction site:
• the area where the construction camp used to be located was completely cleared,
• the temporary fence was removed,
• the slabs and metal structures were removed,
• the kerb was installed,
• the installation of fencing to the left of the site continued.
Inside the building, the weather was no obstacle.
• On the third floor of the office and amenity complex, the floor screed was partially completed, and the ventilation utilities were almost completely assembled.
• Interior glass panels were assembled.
• Installation of the door frames was in progress.
• The formation of the sanitary facilities was underway.
• Heat insulation was put in place in the heat distribution station, the automation cabinets were installed, the control and power supply systems were completed.
The SOLARGROUP back office offers a new opportunity to get coupons for the lottery. To do this, you need to share the referral link to the lottery's landing page, which can be copied here, too.
The person who registers via the link and then invests will become a member of the first level in your partner structure. For every $ 100 in their actual investments, you will get a coupon for the SOLARGROUP lottery.
Participate in the lottery and invite new investors to support the D&E construction and win prizes!
- Art
- Causes
- Crafts
- Dance
- Drinks
- Film
- Fitness
- Food
- Παιχνίδια
- Gardening
- Health
- Κεντρική Σελίδα
- Literature
- Music
- Networking
- άλλο
- Party
- Religion
- Shopping
- Sports
- Theater
- Wellness