​Work on the engineering utilities, landscaping and interior finishing was underway at the construction site last week. 

 

The following work was carried out on landscaping. 

 

• The lawn to the left side and rear of the building was planted. 

• Installation of the permanent fence began. 

• Most of the lampposts were assembled. 

• Kerbstone was installed on the left hand side of the building. 

• The area where the parking lot is to be located was prepared for asphalt paving. 

• 200 dogwood bushes were brought in for planting. 

 

Work on connecting the heat distribution station reached a new stage. 

 

• Some utilities were connected to the heat distribution station. 

• The workers started connecting large diameter pipes. 

• The insulation of pipelines and installation of the automation and telemetry system started. 

 

Work on other utilities was also carried out. 

 

• Tapping of the cold water supply was in progress. 

• The ethylene glycol line was assembled, capped and routed into the building. 

• The drilling to connect the storm sewer was completed. 

• The ventilation utilities were installed. 

 

Finishing works continued in the office and amenity complex. New process equipment was delivered to the site. 

 

The updated SOLARGROUP app is now available on the App Store and Google Play. Now it is available in all languages of the back office. 

 

• The interface of the application has become consistent with the style of the back office. 

• Navigation has been improved. 

• It is now possible to view account status, number of shares, profile and more. 

 

We remind you that the first round of SOLARGROUP prizes-for-all lottery continues in the project in October. Invest to support the "Sovelmash" D&E construction and win an electric car, motorcycle and extra shares!